AI RAN

Active High 2026-08-18 • Deployment AI Grid on RAN
📊 Progress: 16%
📋 Tasks: 4
📅 Start: 2026-07-01
🏁 End: 2026-10-31
Upload Document AI Chat

➕ Add Task

📋 Tasks

4 total
Design & Planing (3 subtasks) End: 2026-08-18 Overdue
100%
IP & VLAN
Openshift Design Cluster
East-West & North South Traffic
Milestone
Phase 1 Complete 📅 2026-08-30
tes123 📅 2026-08-19
Material Delivery (3 subtasks) End: 2026-09-05 On Track
0%
Material On Site
Expedition & Custom
Material Readiness
Milestone
tes 📅 2026-08-25
Physical Intallation (6 subtasks) End: 2026-09-11 On Track
0%
Rack Installation
OOB switch
GPU Server Mounting
Compute Switch (nexus)
Server Management Mounting
Cabling & Power
Milestone
No milestones yet.
Configuration (6 subtasks) End: 2026-10-05 On Track
0%
Compute Switch (nexus)
OOB switch
Routing to CN
Orchestration Server
Compute Server
Armada
Milestone
No milestones yet.

Gantt Chart

Completed On Track In Progress Overdue No Due Date Today
🚧